SUBMISSION PAGE
Program Requirements
Due by September 23, 2022
0.1) Click here for Student Registration
0.2) Click here for submit your school's compiled Parent/Guardian Release and Student Commitment Form packet. (Click here for a a PDF of this form).
Due by December 1, 2022
0.3) Click here to submit your Trades Day information including percentage of Student Attendance and 2-3 Photos OR Trades Day Alternative Activity.
Due by October 7, 2022
0.4) Click here to submit Requests for Information (RFI’s). Answers will be provided on a rolling basis at the Addenda link below.
December 6, 2022
0.5) Presentation Day: Held at Sac State (presentation slides due December 1, 2022, no later than 5 pm).
0.1) Click here for Student Registration
0.2) Click here for submit your school's compiled Parent/Guardian Release and Student Commitment Form packet. (Click here for a a PDF of this form).
Due by December 1, 2022
0.3) Click here to submit your Trades Day information including percentage of Student Attendance and 2-3 Photos OR Trades Day Alternative Activity.
Due by October 7, 2022
0.4) Click here to submit Requests for Information (RFI’s). Answers will be provided on a rolling basis at the Addenda link below.
December 6, 2022
0.5) Presentation Day: Held at Sac State (presentation slides due December 1, 2022, no later than 5 pm).
Deliverable 1 - Due October 14, 2022
Click here to submit Deliverable 1 items (must be submitted at once). This includes:
1.1) Needs Assessment (300-500 words)
1.2) Diagrams/Hand Sketches
1.3) Create a media post about your project concept and tag the Construction Industry Education Foundation
1.1) Needs Assessment (300-500 words)
1.2) Diagrams/Hand Sketches
1.3) Create a media post about your project concept and tag the Construction Industry Education Foundation
Cost Estimate (ONLY) RFI - Due November 1, 2022
Click here to submit RFI's regarding Cost Estimates. All other RFI's must be submitted by October 7, 2022.
Deliverable 2 - Due November 10, 2022
Click here to submit Deliverable 2 items (must be submitted at once). This includes:
2.1) 50% (“half complete”) Construction Document Project Floor Plans
2.2) Selection of Engineering Component
2.3) Cost Estimate - Click here to download an Excel file of the Cost Estimating Pricing Guide
2.4) Field Trip & 2-3 photos
2.5) Trades Component Idea
2.1) 50% (“half complete”) Construction Document Project Floor Plans
2.2) Selection of Engineering Component
2.3) Cost Estimate - Click here to download an Excel file of the Cost Estimating Pricing Guide
2.4) Field Trip & 2-3 photos
2.5) Trades Component Idea
Deliverable 3 - Due December 1, 2022
Click here to submit Deliverable 3 items. This includes:
3.1) Electronic Copy of your Slide Presentation
3.2) Team Video
Trades Day submissions should be made above under 0.3.
3.1) Electronic Copy of your Slide Presentation
3.2) Team Video
Trades Day submissions should be made above under 0.3.